Bauhinia Rail Electrification Project

THE SCOPE | Design and construct two (2) 22kv substations for the Queensland Rail Network.



Design, Manufacture, Deliver, install and test all equipment associated to Kinrola Track Sectioning Cabin and Struan Road Feeder station. Switch yards will be constructed off-site on skids in a modular arrangement; Building will be built and fitted out in a parallel construction sequence. Skid assemblies and Buildings will be connected and pre-commissioned before arriving on site.

Site works will involve simply pick and placement of modules and buildings, control cabling from building marshaling panel to field marshalling panels and minimal OH conductor connections, spot check testing.

 

Download Brochure

Save

Save

Save

Save

Save

Save

 

PROJECT: 1740
CLIENT NAME: Laing O’Rourke / Aurizon
END USER: Kinrola Track Sectioning Cabin and Struan Road Feeder Station
LOCATION: Queensland
INDUSTRY CATEGORY: Mining
CONTRACT TYPE: Design, Construction, Install, Test and Commission
CONTRACT DETAILS: Lump Sum Contract
UPDATES: December 2013 to current