SA Fast Power

RJE Global joined forces with APR to deliver 276MW to the South Australian Power Grid. The project was to install 9 GE TM2500 aero-derivative gas turbine platforms over 2 locations. This was an exciting project as our expert teams in fast power took charge of the Lonsdale and Edinburgh sites. With close to 100 employees engaged to carry out the project, this was completed in 52 days. The project was successfully delivered to our client on time, on budget and incident free. Special thanks to both teams and everyone who supported this project. As usual RJE went above and beyond to ensure a quality product was delivered.

Read More

Local RJE Works Are Underway!

RJE have been engaged as principal contractor to install 4 x 30MW GE TM2500 Gen 8 Gas turbines at Lonsdale & 5 x 30MW GE TM2500 Gen 8 Gas turbines at Edinburgh to provide temporary power generation over the summer months to meet South Australia’s short fall. RJE are on site managing the turbine installation & alignment, turbine package stack out & the mechanical electrical balance of plant assembly & commissioning. We’ve got a great team of people leading this project and will achieve our objective by 1st November 2017. Thanks to all involved in this project for the great work carried out so far.

Read More

Chuuk Power Station Upgrade

The 2 new RJE supplied GE gensets & the relocated CAT gensets have been synchronised to the Chuuk Island power grid & load tested. The client’s representative will witness SAT (site acceptance testing) over the next week in preparation for a handover in mid May.
Our Nick Leach & Josh Smith have been on night shift providing operational support to the customer. Thanks guys!!  Big thanks for the work put in on the project by Mitch Pace, Dylan Johns, Brett Ricketts, Sam White, Lea Pickett & the whole RJE team that has been in country for the duration of the project. Your efforts are always greatly appreciated!!

Read More

Let There Be Light!

A huge milestone achieved on the Chuuk project this week, the new packaged generator units have been connected and commissioned and are now supplying power to the Island.
This is a massive achievement and a credit to the team involved on the project from the initial concept through to design, manufacturing, delivery, installation and commissioning. Well done.

Read More