THE CHALLENGE | The Neurological Hospital in Yangon suffered from unreliable electricity supply and required a full refurbishment and upgrade of the existing Substation.
The Ministry of Health contracted RJE for the following turnkey scope:
- Site clearing, civil works, earthing system, fencing, lighting, auxiliary services.
- Civil design for substation building and site layout
- Electrical design including protection and control systems, cable scheduling and SCADA/HMI integration.
- Installation and commissioning of 2 x 500kVA Power Transformers, 11kV Switchgear, 400V Switchboard, HV Cabling, protection cabinet, SCADA cabinet and control system and capacitor bank.
The successful Substation upgrade at the Neurological Hospital was the first project for RJE in Myanmar. It has provided a blueprint for future upgrades in Yangon, and was an effective showcase for the quality that RJE can provide to the market.